ScanMarine Conclude Transports for Auvere Oil Plant Project
13th September 2024
ScanMarine Estonia is concluding its part in the transportation of technology and equipment for the new Auvere oil plant - 'Enefit 280'.
The largest part of the work was completed in 2023, when most of the equipment for the oil plant arrived at the Port of Muuga.
After the cargo arrived at the Port of Muuga, ScanMarine transported all equipment to the construction site in Auvere.
The widest parts were 5.75 meters in width and 4.95 meters in height.
In this case, the heavy weight was not the issue, but due to the width and height, the transport from Muuga to Auvere had to be carried out at night when there was less traffic on the roads.
The equipment was produced in and shipped from Türkiye with a small number of shipments also coming from China.
The total volume and weight of cargo transported for this project came to 8,000 m3 and 804 T.