The Networking Platform for the World's Top Project Cargo Specialists

Sydney
23:08
Beijing
20:08
Cape Town
14:08
Los Angeles
04:08
Tokyo
21:08
Mumbai
17:38
London
12:08
New York
07:08

Megalift Transporting for Tanjung Bin Power Plant Since 2004

20th April 2022

Megalift Transporting for Tanjung Bin Power Plant Since 2004
Megalift Transporting for Tanjung Bin Power Plant Since 2004

Megalift was the Turnkey Project Logistics Solutions provider for Phases 1, 2 and 3 of the Tanjung Bin Power Plant (2004-2006) and Phase 4 for the Power Plant in 2010.

Last month they were back in Tanjung Bin with a new transformer:

CargoDimensionsWeight
Transformer6.10 m (H) x 5.20 m (W) x 5.30 m (H)265 t

"We arranged the freighting of this 265-ton cargo from India to Jurong Port, Singapore. In Jurong Port, we performed a double banking to discharge the cargo onto a barge from the vessel."

The barge then sailed to Tanjung Bin Power Plant's in-house jetty where Megalift rolled it off to transport the transformer to its final delivery point. This option was chosen as in-land transport was unfeasible due to the cargo’s weight.

At the site, Megalift also performed the jacking and skidding to move the transformer onto its foundation.

http://www.megalift.com.my/